| Introduction | | | | expected to happen. |
| In his Quality Handbook Juran predicted that | | | | Lesson Learned |
| “The 20th century will be remembered as the | | | | If the expectations have been met, the solution |
| Century of Productivity, whereas the 21st | | | | shall be standardized and Lesson Learned |
| century will come to be known as the Century of | | | | Database shall be updated with the solution. The |
| Quality”(Juran, 1999). Maybe the world needs | | | | Project learns when someone, other than the |
| another decade for his prediction to come true. | | | | initial learner, adopts and adapts the new learning |
| Engineering companies in the Oil and Gas industry | | | | or prevention (Wieneke, 2008). |
| have an enormous challenge ahead, in their effort | | | | Then, the organization is doing Knowledge |
| to achieve the desired client success in a dynamic | | | | Management and transforming its own history in a |
| and competitive environment. | | | | list of "Best Practices". |
| In the effort to become a fact-driven company, | | | | Example of a Performance Metric System |
| they implement Key Performance Indicators (KPI). | | | | (KPI) |
| However, one could finds more than 20 articles of | | | | Let’s continue working with the project called |
| firms that are using Bar-Charts to monitor and | | | | ‘SMART’ and the definition of one KPI: |
| display them in a bulletin board. | | | | 7- Schedule Performance Index (SPI): Is a |
| Since the 1920s, Shewhart stressed the | | | | measure of schedule efficiency on a project. |
| importance of controlling the process. Conversely, | | | | An SPI equal to or greater than one indicates a |
| they overlook the Quality Controls Charts that | | | | favourable condition: The Project is ahead of |
| shall be used to determine if a variable or | | | | schedule (SPI > 1) |
| attribute is predictable, stable over time. | | | | An SPI less than one indicates an unfavourable |
| Many professionals used to react to the natural | | | | condition: The Project is behind of schedule (SPI |
| variation as though it were a special cause. Even | | | | < 1) |
| an out of specification situation where the goal or | | | | (I) SPI = Actual Days / Baseline Days |
| target is not being met, is not special cause | | | | SPI can be calculated also using the formula: |
| (Breyfogle, 2008). Therefore, there is nothing to | | | | SPI=BCWP/BCWS |
| worry about unless the variable is out of control. | | | | Where: |
| Last but not least, these kinds of improvement | | | | BCWP- Budgeted cost of work performed |
| initiatives lack of a holistic view, the necessary | | | | BCWS- Budgeted cost of work scheduledif |
| alignment, linkage and replication around the | | | | SPI<1 means project is behind schedule |
| business strategy (Juran, 1999). They only lead to | | | | I used the former one in this example because its |
| firefighting; a reactive culture instead of the | | | | simplicity |
| prevention that organizations need to assure | | | | Using a color-code in a dashboard leads to |
| accountability and value added creation across | | | | firefighting, creating a finger pointing culture |
| engineering disciplines and project phases. | | | | among the project members (Breyfogle, 2008). It |
| The paper structure is as follows: | | | | is necessary to use a professional quality tool: the |
| General Objective: | | | | individual control chart. |
| - To develop a continual improvement framework | | | | Individual Control Chart (XmR) |
| that close the loop, translating problems into an | | | | It is important to emphasize that there are |
| action plan and preventing their recurrence | | | | certain crucial assumptions, which allow the use of |
| Specific Objectives: | | | | this techniques: |
| 1. | | | | 1. The process is in statistical control. |
| To design a continual improvement framework | | | | 2. The distribution of the process considered is |
| describing its implementation steps. | | | | Normal. |
| 2. | | | | If these assumptions are not met, the resulting |
| To develop a Policy Deployment that aligns | | | | statistics may be highly unreliable. |
| project objectives to client expectations. | | | | The results in Excel are similar to a Professional |
| 3. | | | | Statistical Software, the variable SPI is in statistical |
| To design a dashboard performance metric | | | | Control. |
| system (KPI) that lead to root cause | | | | To prove the variable ‘SPI’ follows a |
| analysis and improvement action plans. | | | | normal distribution, the hypothesis is: |
| Continual Improvement Approach | | | | H0: The SPI sample follows a Normal distribution. |
| Almost all Engineering Firms in North America hold | | | | Ha: The SPI sample does not follow a Normal |
| ISO 9001 Certification, mostly for marketing | | | | distribution. |
| purposes. Consequently, only a few have | | | | Figure V shows the results of the normality Test |
| succeeded implementing continual improvement | | | | ‘Anderson-Darling’. As the computed |
| principles due to the complexity of project | | | | p-value (0.317) is greater than the significance level |
| management activities. The following study, | | | | alpha=0.05, one should accept the null hypothesis |
| summarized in the figure I, provides an | | | | H0. The risk to reject the null hypothesis H0 while |
| improvement model for such a complex | | | | it is true is = 31.7%. The variable follows a normal |
| environment. | | | | distribution. |
| | | | The metric is stable. Therefore, the process |
| Figure I describes a continual improvement | | | | capability index (Cpk) can be determined |
| approach designed for EPC firms delivering | | | | Minimum accepted capability: |
| engineering services in the Oil and Gas sector. It | | | | Process capability attempts to answer the |
| has nested PDSA cycles, during all the stages. | | | | question: can we consistently meet customer |
| The challenges that engineering firms are facing | | | | requirements? |
| are immense due to each method of contracting | | | | In a capable process Cpk is 1 or greater. Cpk will |
| affects in its own way the allocation of | | | | be higher only when the variable is meeting the |
| responsibility and the demands on the client side | | | | target consistently, with minimum variation. |
| for coordination and integration of the project | | | | However, considering the characteristics of the |
| flow of knowledge and information in three | | | | EPC industry already mentioned, it is |
| dimensions: vertically, horizontally, and longitudinally. | | | | recommended to accept as a Minimum capability |
| EPC Continual Improvement Approach – To | | | | Cpk = 1. After the organization has applied this |
| Plan | | | | Approach in a whole project phase, it is ready to |
| The Project Scope of Work (SOW) and Contract | | | | replicate the knowledge, reducing variation and |
| are among the inputs for starting the Continual | | | | increasing the minimum capability target. |
| Improvement planning phase. The first step is the | | | | The Figure VII has all the results in only one |
| development of a Project Policy Deployment (a | | | | graph. |
| Strategic Planning methodology, developed by Dr. | | | | The value of Cpk (0.08), in both figure VI and VII |
| Yoji Akao (1988). | | | | means that there is a lot of variation and it is |
| Engineering companies will find that Policy | | | | probable that the organization could not |
| Deployment’s greatest strength is its ability | | | | consistently meet customer requirements in the |
| to translate qualitative, executive level Project | | | | future. Being ‘0.96’ the Lower |
| goals into quantitative, achievable actions (See | | | | Specification Limit for the metric “SPI”, it |
| Table I, below). | | | | is obvious that the performance have been behind |
| | | | schedule in 5 of the last 8 months (SPI > 1). |
| Effective Policy Deployment starts with the client | | | | However, this is just part of the natural variation. |
| requirements of the specific Oil & Gas | | | | Therefore, it means the current process/system |
| Project that is being designed. It shall start with | | | | is incapable of being within specification limits; it |
| the Mission and Vision statements, and develop | | | | has to be redesigned in order to reduce variation. |
| Quality Policy, Critical Success Factors, objectives | | | | |
| and metrics. A future paper will explain the steps | | | | Analysis of ‘SPI’ Variation |
| in the definition of Key Performance Metrics for | | | | The Project Management Institute has found that |
| an EPC project during its various stages and | | | | mature companies have a schedule performance |
| methods of contracting. | | | | index (SPI) variation of 0.08 and a cost |
| Performance feedback: Individual Control Charts | | | | performance index (CPI) variation of 0.11. Less |
| (XmR) | | | | mature companies have corresponding values of |
| The above step creates the foundation for | | | | 0.16 for both indices. |
| managing, measuring and monitoring performance, | | | | The ‘SPI’ Standard Deviation in the |
| while the next step (“Feedback” block) is | | | | “SMART Project” is 0.0875325 (see figure |
| the improvement driver where all the | | | | V). The ‘SPI’ is close to the industry |
| project’s proactive initiatives will initiate. | | | | average, and the variation is due to common |
| The objective of this step is to identify when a | | | | causes. |
| metric is out – of – Control, and conduct a | | | | Conclusions |
| detail analysis of the special causes of variation to | | | | 1. The proposed framework closed the |
| find the Root Cause. | | | | improvement loop, integrating lessons learned and |
| Most of the metrics collected in an EPC | | | | replicating it throughout the whole organization, |
| engineering firm are 'variables' instead of | | | | while achieving the desired alignment with the |
| 'attributes'. The Individual Control Chart – XmR | | | | project strategic deployment. |
| is the one suitable for this kind of observations | | | | 2. If applied properly it will solve critical problems, |
| (conforms to ANSI/ASQC B1-B3 1996). | | | | increasing communication between the project |
| The term special or assignable causes as opposed | | | | team members, and increasing the |
| to chance or common causes was used by | | | | linkage-integration between disciplines and project |
| Shewhart (1939) to distinguish between a process | | | | phases. |
| that is in control, with variation due to random | | | | References |
| (chance) causes only, from a process that is out | | | | ANSI/ASQC B1-B3-1996: Quality Control Chart |
| of control, with variation that is due to some | | | | Methodologies |
| non-chance or special (assignable) factors (cf. | | | | Akao, Yoji, edition (Jap: 1988, Eng: 1991) (in English |
| Montgomery, 1996, p. 102). | | | | (tr. from Japanese)). Hoshin Kanri, policy |
| The XmR utilizes three-sigma control limits and | | | | deployment for successful TQM. New York: |
| indicates an out-of-control signal if a single point | | | | Productivity Press (Originally Japanese Standards |
| falls beyond the control limits. The development of | | | | Association). pp. xiii. ISBN 1-56327 |
| the equations for computing the control chart and | | | | Breyfogle, F. W. (2008), Integrated Enterprise |
| its limits can be found out in Juran (1999) | | | | Excellence, Vol. III Improvement Project |
| Problem Definition and Description: | | | | Execution: A Management and Black Belt Guide |
| The best problem statements make no | | | | for Going Beyond Lean Six Sigma and the |
| assumptions; they simply document the current | | | | Balanced Scorecard, bRIDGEWAY bOOKS, |
| state. | | | | aUSTIN, tx. |
| Craig Cochran (2006) stated that crafting a | | | | Construction Sector Council. 2006-2010 Alberta |
| problem statement is one of the most important | | | | Construction Workforce Supply/Demand Forecast. |
| steps in problem-solving. | | | | May 11, 2006. |
| EPC Continual Improvement Approach – To | | | | Cochran, Craig; (2006).Becoming a Customer |
| Do | | | | Focused Organization, Paton Press |
| The root cause analysis by means of an Ishikawa | | | | Crosby, P.B; (1979) Quality is Free, New York: |
| Diagram will generate several possible solutions. | | | | McGraw-Hill. |
| This phase ends with the Improvement Action | | | | Deming, W.E; (1986) Out of the Crisis, Cambridge, |
| Plan that will be followed until its final resolution. | | | | MA: Massachusetts Institute of Technology, |
| EPC Continual Improvement Approach – To | | | | Centre for Advanced Engineering Studies. |
| Study & To Act | | | | ISO 9001: 2008 - Quality management systems -- |
| Study implies understanding the sources of | | | | Requirements |
| variation in the process (Common vs. special | | | | Juran, J.M; (1999) and F.M. Gryna. Juran’s |
| causes). Therefore, it requires executing the | | | | Quality Handbook, 5th Edition, New York: |
| nested PDSA. | | | | McGraw-Hill. |
| During this stage it is necessary to evaluate the | | | | Maynard's Industrial Engineering Handbook; (2001) |
| benefits of the solution (The “Benefits | | | | 5th Ed, McGraw-Hill, New York, pp. 4.12-4.113 |
| expected” shall be defined in the | | | | Montgomery, D. C; (1996). Statistical quality |
| Improvement Action Plan previously prepared). | | | | control (3rd. Edition). New York: Wiley. |
| Compare what has been found to what is being | | | | |